Record of Oracle implement (2008-08-04)

Tony,

do you recommend to follow this structure to get our scope/costs?

Vladimir





Implement schedule of Oracle.





Hi Vladimir


The following is the preliminary schedule of Oracle.

Do you agree the schedule?

I will give you more details later.

8/04-8/08
(1天) Discuss with end users
1. 配销作业(2Hr)
2. Store management(2Hr)
3. Warehouse management(2Hr)
4. Finance management(2Hr)
5. G/L(2Hr)
6. Costing(2Hr)

8/12-8/15 Proposal

8/12-8/15 Preliminary quote of the project

8/18-8/22
(4Hr) Solution Presentation

8/18-8/22 Quote of the project

8/25-8/29 Evaluate

9/1-9/5 Sign contract

9/1-9/12 Preparing of Kick Off

9/15 Kick Off

Thanks