Tony,
do you recommend to follow this structure to get our scope/costs?
Vladimir
Implement schedule of Oracle.
Hi Vladimir
The following is the preliminary schedule of Oracle.
Do you agree the schedule?
I will give you more details later.
8/04-8/08
(1天) Discuss with end users
1. 配销作业(2Hr)
2. Store management(2Hr)
3. Warehouse management(2Hr)
4. Finance management(2Hr)
5. G/L(2Hr)
6. Costing(2Hr)
8/12-8/15 Proposal
8/12-8/15 Preliminary quote of the project
8/18-8/22
(4Hr) Solution Presentation
8/18-8/22 Quote of the project
8/25-8/29 Evaluate
9/1-9/5 Sign contract
9/1-9/12 Preparing of Kick Off
9/15 Kick Off
Thanks